Projects
Phase I - AESC Offsite Water Improvement
The City of Florence in partnership with the South Carolina Department of Commerce, and Florence County is collaborating to install a new 24-inch water line in support of AESC’s establishment in Florence, SC. The scope of this work involves the installation of a new 24-inch water line of approximately 8,214 linear feet to connect to the existing 30-inch water main at the intersection of Old Marion Highway and East Ashby Road.
The first phase of the new water line installation will terminate along Estate/Koppers Road at the southernmost driveway entrance into the new AESC facility. To date, the project contractor, Complete Utilities, has installed approximately 2,000 linear feet of the new 24-inch water line.
The second phase of the work will include the connection of the new 24-inch water line to the existing 30-inch water line along North Williston Road just south of the Palmetto Paving facility location, which will also involve installing approximately 500 linear feet of the new 24-inch water line along the new Energy Drive to serve the AESC training center.
The project schedule currently has this scope of work being completed and operational by December 2024.
The anticipated cost for the first phase is $3,440,320.00 and is funded through a collective agreement among the South Carolina Department of Commerce, Florence County, and the City of Florence.
Water Distribution System Upgrades
Project Start Date – July 17, 2023
Project Time – December 31, 2024
Project Cost - $2,117,765
Project Contractor – RWF Construction
Project Scope:
City of Florence and AECOM have completed the planning and design that includes a combination of service line replacement replacements and distribution line to improve water service for several neighborhoods in the City of Florence service area. The areas of replacement include Williamsburg Circle, Tara Village, and Grove Park.
The project is part of the city’s continuous effort to upgrade water system infrastructure to maintain quality water service to customers.
East Howe Springs Road AC Waterline Replacement
Project Start Date – April 3, 2023
Project Time – August 1, 2023
Project Cost - $361,718.05
Project Contractor – Complete Utilities
Project Scope:
City of Florence and AECOM have completed the planning and design for the complete installation of approximately 2,596 linear feet of new 6-inch water line along East Howe Springs Road.
The project is part of the city’s continuous effort to upgrade water system infrastructure to maintain quality water service to customers.
West Paul Jones Road Waterline Extension
Project Start Date – March 20, 2023
Project Time – June 19, 2023
Project Cost - $175,774.10
Project Contractor – Complete Utilities
Project Scope:
City of Florence and AECOM have completed the planning and design for the complete installation of approximately 2,964 linear feet of new 6-inch water line and 20 linear feet of new 12-inch water line along John Paul Jones Road.
The project is part of the city’s continuous effort to upgrade water system infrastructure to maintain quality water service to customers.
Surface Water Treatment Plant Filter Media Replacement
Project Start Date – March 2023
Project Completion – April 2023
Project Cost - $219,000.00
Project Contractor – Carbon Activated Corporation
Project Scope:
Furnish all labor, materials, equipment, and incidentals required to remove existing granular activated carbon and sand filter media and replace with new granular activated carbon and sand filter media for filter. Filter is 16.25 ft by 22.0 ft and is to have 4 ft deep new GAC over 1.0 ft deep sand over 0.25 ft deep torpedo sand plus extra media for stock and skimming for all media as defined.
The project is part of the city’s continuous effort to upgrade water system infrastructure to maintain quality water service to customers.
Airport Tank Rehabilitation Construction
Project Started – 2023
Project Completion – 2023
Project Cost - $269,000
Project Contractor – Viking Painting, LLC
Project Engineer – AECOM, Columbia, SC
Project Scope:
The City of Florence Airport elevated water tank, located on South Greer Road. This is a 300,000-gallon tank including painting the interior and exterior and replacing the tank components, handrails, and piping. After the tank is thoroughly disinfected to regulatory standards and bacteriological samples were collected, the tank will be filled with treated water and put back into service.
The project is part of the City’s continuous effort to upgrade water system infrastructure and maintain quality services to customers.
McCown Tank Rehabilitation Construction
Project Started – March 28, 2022
Project Completion – October 17, 2022
Project Cost - $490,000
Project Contractor – Scott I. Enterprises
Project Engineer – AECOM, Columbia, SC
Project Scope:
The City of Florence Pine Needles elevated water tank, located on 2992 Third Loop Road. This is a 500,000-gallon tank including painting the interior and exterior and replacing the tank components, handrails, and piping. After the tank is thoroughly disinfected to regulatory standards and bacteriological samples were collected, the tank will be filled with treated water and put back into service.
The project is part of the City’s continuous effort to upgrade water system infrastructure and maintain quality services to customers.
Timmonsville Sanitary Sewer Rehabilitation Phase II
Project Overview
City of Florence and AECOM have completed the planning and design for Timmonsville Sanitary Sewer Rehabilitation Phase II sewer project for improvements along the following roadways: Warren Street, Orange Street, Keith Street, Pinckney Street, Hill Street, Byrd Street, New Street, Park Street, and Brockington Street. The project bid was awarded to Insituform Technologies, LLC.
The purpose of the sanitary sewer system improvements for the City of Florence – Timmonsville is to repair and replace aging infrastructure. The anticipated project includes:
- Warren Street – 966 linear feet (LF) of cured-in-place pipe (CIPP) 8” gravity sewer, 1 manhole rehabilitation and 10 services
- Orange Street – 1,371 LF of CIPP 8” gravity sewer, 410 LF of root removal,
2 point repairs, and 30 services
- Keith Street – 1,452 LF of CIPP 8” gravity sewer, 376 LF of pipe bursting 8” gravity sewer, 3 point repairs and 3 manhole rehabilitations and 38 services
- Pinckney Street – 1,840 LF of CIPP 8” gravity sewer, 2 manhole rehabilitations and 11 services
- Hill Street – 321 LF of CIPP 8” gravity sewer and 4 services
- Byrd Street – 497 LF of CIPP 8” gravity sewer, 305 LF of CIPP 12” gravity sewer, 295 LF of pipe bursting 8” gravity sewer, 125 LF of root removal, 2 point repairs, 3 manhole rehabilitations and 13 services
- New Street – 676 LF of CIPP 8” gravity sewer and 9 services
- Park Street – 369 LF of new 8” gravity sewer, 2 new manholes, 1 manhole rehabilitation and 6 services
- Brockington Street – 257 LF of pipe bursting 8” gravity sewer and 3 services
Schedule
Construction is estimated to start March 14, 2022 and take 180 days to complete (construction schedules are subject to change due weather and other conditions).
Project Goal
This project will improve wastewater carrying capacity and reliable service for current and future customers.
Project Cost
$1,254,441.70
Alligator Road Water Plant Filter Vessel Rehabilitation Construction Project
Project Award Recommendation – June 21, 2021
Project Started – August 9, 2021
Project Completion – January 18, 2022
Project Cost - $173,600.00
Project Contractor – North American Construction
Project Engineer – AECOM, Columbia, SC
Project Scope:
The City of Florence Alligator Road Water Plant Filter Vessel Project is located at 3422 Alligator Road. The work includes the removal and replace one (1) filter four (4) cells support gravel, sand and anthracite, and sandblast and paint one (1) filter four (4) cells interior and overcoat paint filter exterior and piping.
The project is part of the City’s continuous effort to upgrade water system infrastructure and maintain quality water service to customers.
Pine Needles Tank Rehabilitation Construction
Project Award Recommendation – December 2, 2021
Project Started – January 2, 2021
Project Completion – June 14, 2021
Project Cost - $405,000
Project Contractor – Scott I. Enterprises
Project Engineer – AECOM, Columbia, SC
Project Scope:
The City of Florence Pine Needles elevated water tank, located on 3459 Pine Needles Road, is now complete and back online. This 500,000-gallon, 21-year-old tank underwent repairs, including painting the interior and exterior and replacing the tank components, handrails, and piping. After the tank was thoroughly disinfected to regulatory standards and bacteriological samples were collected, the tank was filled with treated water and put back into service on June 14, 2021.
The project is part of the City’s continuous effort to upgrade water system infrastructure and maintain quality services to customers.