WASTEWATER TREATMENT DIVISION
General Instructions for Completing and
Submittal of
DISCHARGE MONITORING REPORTS
The South Carolina Department of Health
and Environmental Control (SCDHEC) provides each permitted discharger a
Discharge Monitoring Report (DMR) form. The DMRs are preprinted with the
permittee's address, facility name, location, permit number, discharge
pipe number, a DMR valid date, and the parameters to monitor. This
information should be reviewed carefully to be sure it is correct. Any
discrepancies should be reported to the SCDHEC NPDES Administration
Section at 734-5233 or734-5234.
DMRs must be postmarked by the 28th
day of the month following the report month; i.e. the DMR for sampling
conducted in January must be postmarked by February 28th.
A DMR is required for each month, even if the facility is not
operational or is under construction.
If there is no discharge for the entire reporting period, write
"NO DISCHARGE" across all pages for that outfall.
-
The dates in the "Monitoring Period" section of the DMR form
must be filled in for the monitoring period being reported.
Monitoring periods typically cover a one-month period, but may be
for a quarter, year, etc. The
"FROM" date is the first day of the monitoring period and the "TO"
date is the last day of the monitoring period.
To restate that another way, the monitoring period covers the first
day of the period through (including) the last day of the period.
For Example: A
DMR for the month of June 1994 would list a "FROM" date as 94/06/01
and a "TO" date as 94/06/30. Even
if the facility did not discharge for the entire month, the monitoring
period is still the first day of the month to the last.
If a permit requires quarterly
reporting with an effective date of, say, February 1, 1994, the "FROM"
date would be 94/02/01 and the "TO" date would be 94/04/30.
Monitoring periods for those permits with quarterly, annual, or
other requirements begin on the effective date of the permit.
If the discharge is shorter than the reporting period, explain the
duration of the short discharge in the comments section of the DMR.
Permits now specify a monitoring day in Part III.
If a facility is not discharging on that specified day, but
discharges at some other time during the month, you are still required to
monitor the discharge.
-
Fill in all open boxes of the sample measurement section under
average, maximum and minimum columns.
The permit limits are listed in the shaded (gray) boxes.
The open boxes must be filled in with the results.
If a parameter (permit limited item, such as lead, pH, etc.) is not
monitored, "NOT SAMPLED" should be written across that line of the DMR.
For each parameter, the "LAB ID" (Laboratory Identification
Number) for the laboratory conducting that analysis must be reported.
-
Fill in the "NO EX" (number of exceptions) block with number of
sample measurements during the monitoring period that exceed the maximum
(and/or minimum or seven day average as appropriate) permit requirement
for each parameter. The number should be the total of all exceptions during the
reporting period; this includes loading and quality or concentration
limits. If no violations have
occurred during the reporting period, enter "0".
For Example: If
your facility has permit limits for BOD of 30 mg/l monthly average, 45
mg/l weekly average, you are required to monitor BOD once per week and the
following results are obtained: your
BOD for the first week is 48 mg/l and the BOD results for the remaining
weeks of the month are 20 mg/l, then you would report "1" in the "NO
EX" column. The one
exception being the weekly average of 48 mg/l which occurred during the
first week.
Given the above example where the first week's BOD value is 48
mg/l, if the second week's BOD
Result is 46 mg/l with the remaining weeks at 20 mg/l, the "NO
EX" would be "3", with 48 being
the reported
value for the maximum weekly average.
The three exceptions being 48 mg/l and 46 mg/l weekly averages
exceeding the limit of 45 mg/l and the monthly average value of 34 mg/l
(48+46+20+20/4=34) exceeding the limit of 30 mg/l.
These examples assume that there are no mass or quantity (pounds)
violations for the parameter. If
there were BOD mass violations, they too would be included in the total
reported in the "NO EX" column.
-
Enter the "Frequency of Analysis" used during the monitoring
period. This is the actual
number of times samples were collected and analyzed.
For Example: If
a facility is required to monitor a parameter once per week, they may have
sampled more frequently, say, five times per week, the reported
"Frequency of Analysis" would be 05/07, while the permit frequency is
listed as 01/07. Likewise, if
the required frequency is daily (listed as 01/01), but due to unforeseen
circumstances samples were only collected for 23 days out of a possible
30, then the correct "Frequency of Analysis" would be 23/30.
In this example an explanation for the reduced frequency must be
included in the comment section or on an attached sheet.
Some of the more common "Frequency of Analysis" codes include:
01/YR…ANNUAL
01/01…DAILY
01/07…WEEKLY
01/90…QUARTERLY
02/30…TWICE/MONTH
05/07…WEEKDAYS
-
Enter the "Sample Type". This
is the actual sample type used during the monitoring period.
It should be the same as the listed permit requirement.
For Example: If
the required sample type is "GR" (for Grab), and a grab sample is
collected, then "GR" should be entered in the "Sample Type" block.
However, if the required sample type calls for "24" (for 24
hour composite), but a grab sample is collected, then "GR" would be
entered in the "Sample Type" block and an explanation as to why the
sample type was different from that required included with the DMR.
Some of the more common "Sample Types" include:
CN…CONTINUOUS
CP…COMPOSITE
GR…GRAB
IN…INSTANTANEOUS
RC…RECORDER
16…16 HOUR COMPOSITE
24…24 HOUR COMPOSITE
-
The Principal Executive Officer's name and title must be printed
or typed in the block provided. This
is the responsible official for the facility, NOT the operator.
The DMR must be signed by the Principal Executive officer or an
Authorized Agent. A signature
stamp is not acceptable. Please
use an ink color other than black so as to help distinguish the original
from copies.
-
The date the DMR is prepared must be entered in the appropriate
blocks on the form.
Mail the completed DMR form (one
original and a copy) to the:
S.C. Department of Health and Environmental Control
Bureau of Water
Compliance Assurance Division
2600 Bull St.
Columbia, S.C. 29201
Be sure to retain a copy for your
records. Federal regulations
require that these records be retained for a minimum of 3 years.
IMPORTANT POINTS TO REMEMBER
The units reported must be the same as
those listed in your NPDES permit. A
common error by permittees is to report flow in units other than Million
Gallons per Day (MGD). If the
permit specifies MGD, then the flow must be reported in MGD.
For Example:
2000 gallons per day is to be reported as .002 MGD.
All copies must be legible.
Many facilities prefer to use computer
generated DMR forms. Sample
forms must be submitted and approved by the Department prior to the
permittee using the forms for reporting purposes.
DMRs reported on unapproved forms will not be accepted.
|